Timeline of accomplishments:
- Fall 2006
Students identify operational space needs for student government and services. Students develop concepts and determine support among student leaders. Student leaders presented a request for conceptual approval of site request to the Campus Planning Committee. CPC approves.
- Winter 2007
Located funding for architectural assessment and conceptual design of MU Annex
- Spring 2007
Selected architect for conceptual design study (Opsis Architecture of Portland)
- Summer 2007
Conducted focus groups with MU East student organizations and staff members
Timeline of next steps:
- Fall 2007
Annex proposal and preliminary site development plan will be presented to students
Present plan to Campus Planning Committee for approval
- Winter 2007
If approved by CPC, present funding proposal to students for all-campus student vote
- Spring/Summer 2008
Develop plans for MU Phase III renovation
- Fall 2008/Winter 2009
Bid construction for Memorial Union Phase III and Fire and Life Safety upgrades
- Spring 2009
Develop plans for MU Annex construction
- Summer 2009 thru Summer 2010
MU Phase III renovation
Bid construction of MU Annex
- Fall 2010 thru Summer 2011
Construction of the MU Annex building
- Fall 2011
Occupy new MU Annex building
|